Playground Equipment at Community Center Replacement Timetable

Reported by Mike Hanson

We are replacing the playground equipment at the playground next to the Community Center.
The planned timetable is:
Monday June 18th – Close the playground for prep work.
June 27th – New equipment is scheduled to arrive.
June 27th & 28th – Installation.
June 29th – Reopen.

Preparations for the new equipment include:

Removal of the current equipment, and pushing the sand aside.

As usual with outdoor projects, the schedule is weather dependent.

Let’s hope all goes smoothly and on schedule.